Installation Overview
Page 2-3
Installation
Overview
Table 2-1 describes the steps needed to install the IntraSwitch
5308FL.
The steps that are optional are labeled “optional”; the steps that
are required are labeled “required.” The sections that follow
explain each step in detail.
To install the IntraSwitch 5308FL:
Table 2-1 Installation Overview
Step Action
1 (required) Open the box and check the contents.
See “Package Contents” on page 1-8 for a
complete list of the items included with your
IntraSwitch 5308FL.
2 (required)
Install the IntraSwitch 5308FL in an equipment
rack or prepare it for desktop placement.
See “Rack Mounting/Desktop Placement” on
page 2-4.
3 (optional)
Install MII module(s), if any.
See “Installing MII Modules” on page 2-6.
4 (required)
Check the power connection.
See “Connecting Power” on page 2-8.
5 (required)
Connect the IntraSwitch 5308FL to the network.
See “Connecting to the Network” on page 2-9.
6 (optional)
Configure the IntraSwitch 5308FL for
management capabilities.
See “Setting up for Management” on page 2-12.