4-20 SPARC Enterprise M8000/M9000 Servers Service Manual • June 2010
4.4.2.2 From the Maintenance Terminal
Follow the power-on procedure below using the XSCF maintenance functions.
1. Make sure that the server has enough power supply units to run the desired
configuration.
2. Switch on all main line switches of the AC section.
3. Make sure the XSCF Unit Ready LED is lit.
4. Log into the XSCF Shell and type the poweron command.
Refer to the SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF
User’s Guide for details.
5. After a delay the following activities occur:
■ The operator panel Active LED will light.
■ The system will execute the power-on self-test (POST).
Then, the server is completely powered on.
6. Turn the keyswitch on the operator panel to the Locked position.
4.4.3 Confirming the Hardware
1. Use the showhardconf command to confirm the new component has been
installed:
XSCF> poweron