Fujitsu M8000 Server User Manual


 
6-22 SPARC Enterprise M8000/M9000 Servers Service Manual June 2010
b. Exit the maintenance menu.
18. Configure the CMU into the system.
Active replacement:
Use the addboard command to dynamically configure the relevant CMU into
a domain. Perform this operation for all the domains that have been recognized
in Step 2 as including the CMU to be replaced.
For details, see Section 4.2.2, “Disconnecting and Replacing a FRU” on
page 4-5, and the SPARC Enterprise M4000/M5000/M8000/M9000 Servers
Dynamic Reconfiguration (DR) User’s Guide.
Hot replacement:
From the console that is connected to XSCF, execute the poweron -d
command of XSCF to turn on power to the domain.
When the power to the domain is turned on, version synchronization of
OpenBoot PROM (OBP) is automatically performed. When version
synchronization is completed, the power-on self test (POST) is performed.
When ok prompt displayed on the console of relevant domain, POST is
completed.
19. Confirm that the replacement components are normal by using the
showhardconf or showstatus command of XSCF.
Unless "*" is displayed for a replacement CMU, CPU, or DIMM, it is operating
normally.
For details of the showhardconf command and showstatus command, see the
SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF User’s Guide,
the SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF Reference
Manual, or the man page.
Note – The showstatus command displays information on degraded components.
20. Close the door on the server, and lock it.