American Power Conversion PD80KF6FK1-M Power Supply User Manual


 
System Operation
40 80kW InfraStruXure PDU—Operation and Configuration
4. Ensure that all battery units are pushed all the way into the XR Battery Enclosures and locked
into position.
5. Set the XR Battery Enclosure DC Disconnect
circuit breaker to ON.
6. Set the UPS System Enable switch to ON
When the System Enable switch is placed in the ON position, the Startup screen appears on the
display interface of the Symmetra PX UPS.
The top-level status screen appears on the display interface. This may take up to 30 seconds.
PowerView RM
Rev: 000 English
Please wait...
Fuel%
Load%
Runtime:
||||||||||||
|||
1hr 2m
In 208V out000V 60Hz