Powerware 9330 (10 kV A--40 kVA) Installation and Operation
164201300 REV. G 061502
1-- 3
1.1.5 Inspecting and Unpacking Each Cabinet
The first task in preparing for installation is inspecting and unpacking the UPS
sections. The UPS and accessory cabinets are shipped bolted to wooden pallets,
a s s h o wn i n F i g u res 1 --- 1 o r 1 --- 2 , a n d p r o t e c t ed with o u t e r p ro t ective packagi n g
material.
Figure 1 ---1. Powerware 9330 (10 kVA ---20 kVA) UPS Cabinet as Shipped on Pallet