Powerware 9330 Power Supply User Manual


 
2-- 28
Powerware 9330 (10 kV A--40 kVA) Installation and Operation
164201300 REV. G 061502
NOTE: Remove Options cabinet PDM conduit landing plate to punch conduit holes.
15. Install Square-D Type QO or QOB breakers into PDM panelboard. Refer to
Appendix A of this manual for access information.
16. Wire branch circuits in accordance with branch circuit breaker manufacturers
instructions (output from the UPS or Options cabinet is prewired to the PDM).
Refer to Appendix A of this manual wiring access information.
17. After wiring the Options cabinet to the facility power and critical load, be sure
to ground the system according to local and/or national electrical wiring codes.
18. When all wiring is complete, connect battery strings in accordance with
instructions contained in paragraphs 3.4.1 and 3.4.2 of Chapter 3.
19. Secure the UPS by reinstalling safety shield panels, front vented panels, and
front solid panel.
20. Install side panel removed from the UPS cabinet to the left side of the Options
cabinet.
21. Secure the Options cabinet by reinstalling front vented panel.
2.5 Initial Startup
Startup and operational checks should be performed only by authorized service
personnel. Contact service in advance (usually a two week notice is required) to
reserve a preferred startup date.
2.6 Completing the Installation Checklist
The final step in installing your UPS system is completing the following Installation
Checklist. This checklist ensures that you have completely installed all hardware,
cables, and other equipment. Completing all items listed on the checklist will
ensure a smooth installation. You should make a copy of the Installation Checklist
before filling it out, and retain the original.
After your installation is complete, a service representative will be able to verify the
operation of your UPS system and commission it to support your critical load. The
service representative cannot perform any installation tasks other than verifying
software and operating setup parameters. Service personnel may request a co py
of the completed Installation Checklist to be sure you have completed all
applicable equipment installation.
NOTE: The Installation Checklist MUST be completed prior to starting the UPS
system for the first time.