Toshiba G9000 Power Supply User Manual


 
70 G9000 Installation and Operation Manual
EMB
CPMS
CPMC
3.4 OPERATING PROCEDURES
For Parallel Operation system, refer to section D) MMS Start-up Procedure”.
(Parallel Operation system is herein after MMS [Multi Module System])
A) Start-up Procedure
Before the UPS startup, the internal Bypass line starts to supply the unconditioned bypass
input power to the load if the External input (or Bypass) Circuit Breaker is closed. Be
extremely careful with closing the External input (or Bypass) Circuit Breaker.
Confirm the position of the circuit protectors (CPMC, CPMS and EMB) located at the upper
part of the cabinet (FIGURE 3.8).
1) CPMC and CPMS: ON; 2) EMB: OFF.
FIGURE 3.8 Circuit protectors location
a.) Verify that the External Bypass Input Circuit Breaker for each unit is closed.
(user supplied)
b.) Verify that Battery Disconnect Circuit Breaker (CB2) is opened or in tripping position.
c.) If a dual source is feeding the UPS, close the External AC Input Circuit Breaker manually (user
supplied).
d.) The LCD panel boots up automatically, and the screen will show that the Load is powered by
bypass line.
e.) On the LCD panel, select OPERATIONtab, and then press the STARTUP GUIDANCEbutton
to continue UPS start-up. (Refer to Figure 2.3)
f.) Follow the STARTUP GUIDANCEaccordingly until the completion of the inverter startup.
When "REMOTE OPERATION MODE" is displayed on the LCD panel, the inverter start
operation can only be performed remotely. If local inverter start operation is required (at the
UPS), select "LOCAL ONLY" or REMOTE & LOCALin the OPERATION MENU.
!
NOTE
!
NOTE