72 G9000 Installation and Operation Manual
C) Bypass Operation Procedure
** Transfer from Inverter to Bypass
1. Check for SYNCon the LCD.
2. Press the "START/STOP” icon on the LCD.
3. Follow the SHUTDOWN GUIDANCEand Press the "STOP" icon on the LCD.
** Transfer from bypass to inverter.
UPS
1. Press the "START/STOP" icon on the LCD.
2. Follow the STARTUP GUIDANCEand Press the "START" icon on the LCD..
When "REMOTE OPERATION MODE" is displayed on the LCD panel, the inverter
start operation can only be performed remotely. If local inverter start or stop operation is
required (at the UPS), select "LOCAL ONLY" or REMOTE & LOCALin the
OPERATION MENU.
!