61189500L1-1B PRELIMINARY 4-1
Section 4
Installation
GENERAL
The first three tasks for installing and operating the MX410/MX412 are to unpack, inspect,
and install. Those tasks are detailed in this section of the manual, as well as information for
mounting the MX410/MX412 into an equipment rack or to a wall, making the proper connec-
tions to the front and back panels, identifying the front panel indicators, and adding or
removing a Power Supply Unit (PSU) (MX410 only).
RECEIVING INSPECTION
Inspect the MX410/MX412 for any damage that might have occurred in shipment. If damage
is suspected, file a claim immediately with the carrier, keep the original packaging for damage
verification and/or returning the unit, and contact ADTRAN Customer Service. For warranty
information, refer to “Appendix A, Warranty”.
ADTRAN SHIPPING CONTENTS
After unpacking the MX410 or MX412 but before an initial power up, be sure that the
following items are present:
• MX410 and MX410 PSU
or
MX412
• Mounting brackets and screws for 19-inch rack or wall installation
– Ground lug with nut and lock washer
– Wire-wrap post cover and screw
– Power connector
– Blank PSU cover (MX410 only)