Hot-plug components
● If a 10 Gb Ethernet mezzanine card is installed in slot 1 of a server blade, at
least one 10 Gb Ethernet connection blade must be installed in CB slot 2 of
the system unit.
● If an FC mezzanine card is installed in slot 1, at least one FC connection
blade must be installed in CB slot 2.
● If a 1 Gb Ethernet mezzanine card is installed in slot 2 of a server blade, at
least one 1 Gb Ethernet connection blade must be installed in CB slot 3 or
in CB slot 4 of the system unit.
● If a 10 Gb Ethernet mezzanine card is installed in slot 2 of a server blade, at
least one 1 Gb Ethernet connection blade must be installed in CB slot 3 or
in CB slot 4 of the system unit.
● If an FC mezzanine card is installed in slot 2, at least one FC connection
blade must be installed in CB slot 3 or in CB slot 4.
● If an Infiniband mezzanine card is installed in slot 2, an Infiniband connection
blade should be installed in CB slots 3 and 4.
I In this case, both channels of the Infiniband mezzanine card are
used.
● You can install a combination of FC, Ethernet and Infiniband mezzanine
cards in a server blade. In this case, the Ethernet mezzanine card should be
installed in slot 1 and the FC or Infiniband mezzanine card in slot 2 of the