Initial Startup Checks and Commissioning Procedure for Warranty Inspection
109
11.1 Information for Warranty Inspection—Remove Power From Unit Disconnect
Complete the following items on the warranty inspection form:
Installer and address
Owner and address
Site Contact name and phone
Installation date
Indoor unit model and serial number
Outdoor unit (condenser or drycooler) model and serial number
Condition of unit when received
Is there a freight damage claim in process?
Have manuals been kept with unit?
Is the air product connected to site monitoring or switchover controls?
Provide model and serial of connected controls for switchover controls
11.2 Startup Checks Inspection With Panels Removed and Disconnect Off
1. Check all internal piping clamps and tighten or secure if needed.
2. Check field piping for proper support
3. Check unit belts for correct tension and alignment.
4. Check unit electrical connections and tighten or secure if needed. Check control plugs and
Mate N’ Loc connections to the control boards and components.
5. Check all major components such as compressors, reheats, humidifiers and motors that may have
loosened during shipping.
6. Remove shipping blocks from compressor(s) / adjust spring tension.
7. Remove all debris, tools and documents from unit area.
8. Record main fan horsepower and voltage from nameplate, record belt size, motor sheave and fan
pulley.
9. Record filter size and quantity
10. Record piping size for discharge and liquid lines,.
11. Check piping for proper traps including inverted traps on condensers.
12. Record total equivalent length for discharge and liquid piping.
13. Record compressor(s) model and serial number.
14. Record unit configuration and verify with the startup document.