2. BitStorm 1900 Installation and Testing
2-96 BitStorm 1900 Installation and Maintenance Guide 1900-A2-GN20-00
Task 014: Testing the BitStorm 1900 Installation
Testing a BitStorm 1900 installation includes the following tasks:
• Testing voice connectivity
• Testing data connectivity
• End-to-end connectivity
The following sections contain testing-related information followed by
the BitStorm 1900 testing tasks. Testing tasks for network support
equipment such as LAN/WAN routers are not included in this
document.
BitStorm 1900 Testing Locations
Primary test points for installation include the following:
• Customer premises cross-connect containing the connections for
the BitStorm 1900 and customer premises equipment
• Modem user locations
If the system is having trouble, other test points may be required.
Step Procedure
1.) Review the BitStorm 1900 Test Point Diagrams as follows:
• Figure 2-21, "Voice/Data System Test Points," on page 97
shows the schematic layout and primary test points of a
BitStorm 1900 voice/data system.
• Figure 2-22, "Data-only System Test Points," on page 98 shows
the schematic layout and primary test points of a BitStorm 1900
data-only system.