Allied Telesis X600-24TS/XP Switch User Manual


 
Chapter 4: Cabling the Network Ports
82
Installing SFP/XFP Transceivers
Review the following guidelines before installing an optional SFP or XFP
transceiver in a switch:
A transceiver can be hot-swapped; the switch can be powered on
when you install it. However, you should always disconnect the cables
first before removing a transceiver.
You must install the transceiver before you connect the cables to it.
Fiber optic transceivers are dust sensitive. When a fiber optic cable is
not installed, or when you store the transceiver, always keep the plug
in the optical bores. When you do remove the plug, keep it for future
use.
Unnecessary removal and insertion of a transceiver can lead to
premature failure.
Warning
A transceiver can be damaged by static electricity. Be sure to
observe all standard electrostatic discharge (ESD) precautions,
such as wearing an antistatic wrist strap, to avoid damaging the
device.
Installing an SFP
Transceiver
To install an SFP transceiver in an x600 switch, perform the following
procedure:
1. Remove the dust plug from a transceiver slot on the switch, as shown
in Figure 40.
Figure 40. Removing a Dust Plug from an SFP Slot
1322
23R
24R
CLASS 1
LASER PRODUCT
D/C
L/A
1000 LINK / ACT
FDX
PORT A
25
XFP
SFP
21 22
23 24