Extreme Networks 8800 Series Switch User Manual


 
Site Preparation
BlackDiamond 8800 Series Switches Hardware Installation Guide
68
Monitor and log power supply status.
Display the voltage (current draw) of the equipment.
Restart equipment after a long power outage.
Display the voltage currently on the line.
Provide alarms on certain error conditions.
Provide short circuit protection.
Selecting a UPS
To determine UPS requirements for your switch, answer these questions:
What are the amperage requirements?
What is the longest potential time period that the UPS would be required to supply backup power?
Where will the UPS be installed?
What is the maximum transition time that your installation will allow?
NOTE
Extreme Networks recommends that you use a UPS that provides online protection.
Calculating Volt-Amperage Requirements
To determine the minimum volt-amperage requirements for your UPS:
1 Locate the voltage and amperage requirements for each piece of equipment. These numbers are
usually located on a sticker on the back or bottom of your equipment.
2 Multiply the numbers together to get Volt-Amps (VA):
VA = Volts x Amperes
3 Add together the VA from all the pieces of equipment to find the total VA requirement.
To determine the minimum volt-amperage requirements for your UPS, we recommend that you add
30% to the total.
UPS Transition Time
Transition time is the time that is necessary for the UPS to transfer from utility power to full-load
battery power. For Extreme Networks products, a transition time of less than 20 milliseconds is required
for optimum performance.
Applicable Industry Standards
For more information, see the following ANSI/TIA/EIA standards:
ANSI/TIA/EIA-568-A—discusses the six subsystems of a structured cabling system.
ANSI/TIA/EIA-569-A—discusses design considerations.
ANSI/TIA/EIA-606—discusses cabling system administration.
ANSI/TIA/EIA-607—discusses commercial building grounding and bonding requirements.