GE GFK-1541B Network Card User Manual


 
GFK-1541B Chapter 2 Installation 2-45
2
Installing the CMM742 in the PLC
For general information about module and system installation, refer to GFK-0262,
Series 90-70
Programmable Controller Installation Manual
.
Equipment Required to Perform the Installation Procedures
Make sure you have the items listed below before you begin.
Series 90-70 PLC rack.
Series 90-70 power supply.
To use the AUI port, the power supply must be one of the following types, which
provide +12 Vdc for an external transceiver on the AUI port: IC697PWR711,
IC697PWR724, or IC697PWR748.
If the AUI port will not be used, +5 Vdc is all that is required. Under these conditions,
power supply IC697PWR710 is sufficient.
A Series 90-70 CPU.
PLC programming software: Logicmaster 90-70 version 6.02 or higher or Control version
1.0 or higher (runs on a personal computer).
Ethernet cables and, if using the AUI port, an Ethernet-compatible AUI transceiver. (See
Appendix B, “Communications Ports Characteristics”, for more information.)
A serial cable for the Station Manager port on the Ethernet Interface (see Appendix B).
Optional
A terminal or IBM-compatible personal computer equipped with terminal emulation
software. Optional
A Phillips-head screwdriver.
Note
If your installation requires CE Mark compliance, please refer to GFK-1179,
Installation Requirements for Conformance to Standards
, shipped with the PLC
programming software, for additional guidelines.