3.4.1.3 Estimated Schedule for ABC Responsibilities
The following is an estimated schedule for the ABC responsibilities. The actual
schedule will be determined at project start.
Table 5. ABC Responsibilities
Month Number
Month Initial
1 2 3 4 5 6 7 8 9
J J A S O N D J F
01 - Manage ABC Conversion Responsibilities ** ** ** ** ** ** ** ** **
02 - Participate in Project Planning
* * * *
*
03 - Operate MVS Environment ** ** ** ** ** ** ** ** **
04 - Provide Office Space and Project Support
Tools
*
05 - Determine and Supply VSE Material to be
Converted
* * * * * * * *
06 - Assist with Conversion Specifications
**
** **
**
07 - Apply Manual Modifications to VSE
Material (If any)
* * *
08 - Set up MVS Operations Tools ** ** ** ** **
09 - Perform Online Application Tests ** ** ** **
10 - Perform Batch Application Tests * ** ** ** *
11 - Participate in Applications Switchover to
MVS
** *
12 - Support Initial MVS Operations **
3.4.1.4 Estimated Schedule for SER Responsibilities
The following is an estimated schedule for the SER responsibilities. The actual
schedule will be determined at project start.
Table 6. SER Responsibilities
Month Number
Month Initial
1 2 3 4 5 6 7 8 9
J J A S O N D J F
01 - Provide MVS Resources * * * *
02 - Install, Maintain, and Support MVS
Environment
** ** ** ** ** ** ** ** **
03 - Assist with Conversion Specifications
**
** **
**
04 - Participate in Applications Switchover to
MVS
** *
05 - Support Initial MVS Operations **
Chapter 3. Developing the Plan 55