ID Task Name Projected Actual
Start End Start End
72 Batch Application Tests Can Start 06/07/98 06/07/98
73 Perform Critical Application Batch Tests 06/07/98 08/16/98
74 Non-critical Application Batch Tests 08/16/98 09/21/98
75 Refine New OS/390/DFSMS Standards 05/10/98 08/16/98
76 Identify Application Interfaces 06/14/98 08/02/98
77 Refine & Repeat Batch Application
Conversion
05/10/98 08/16/98
78 Switchover Preparation 07/19/98 09/21/98
79 File Migration 07/19/98 08/16/98
80 Develop Switchover File Migration Specs 07/19/98 08/02/98
81 Develop Switchover File Migration
Procedures
08/02/98 08/16/98
82 Switch Rehearsal Can Start 08/16/98 08/16/98
83 Rehearse Switchover File Migration 08/16/98 08/17/98
84 Production Tests 08/17/98 09/21/98
85 Perform Production Tests 08/17/98 09/21/98
86 Actual Conversion 08/17/98 09/21/98
87 Convert Development Code 08/17/98 08/30/98
88 JCL Supply For Last Mass Conversion 08/22/98 08/23/98
89 Last Mass JCL Conversion 08/24/98 08/30/98
90 Fix & FreezeJCL 08/24/98 09/21/98
91 Program Supply for Last Mass Conversion 09/09/98 09/10/98
92 Last Mass Program Conversion 09/11/98 09/12/98
93 Freeze & FixPrograms 09/11/98 09/21/98
94 Switchover Can Start 09/21/98 09/21/98
95 OS/390 Switchover 09/21/98 10/23/98
96 Final Switchover Preparation 09/21/98 09/26/98
97 Actual Switchover Weekend 09/26/98 09/26/98
98 Assist OS/390 Operations 09/28/98 10/23/98
99 Project End 10/23/98 10/23/98