70 Installation and configuration
553-3001-358/555-4001-135 Standard 02.00 July 2006
3 Plug the DB-25 male connector at the other end of the terminal cable into the
DB-25 female connector of the customer-supplied DB-25F/DB-25M
nullmodem adapter.
4 Plug the DB-25 male connector of the DB-25F/DB-25M nullmodem adapter
into the DB-25 female connector on the modem.
5 Insert the modular RJ11 plug into the RJ11 jack on the modem.
This procedure is now complete
6 Insert the other end of the RJ11 plug into the RJ11 jack on the wall.
Procedure 10
Access the ICB remotely using a LAN hub – Option 11C or CS 1000
1 Verify that the Ethernet Adapter/MAU is installed in the Option 11C or CS
1000. Insert the industry-standard MAU into the Ethernet Connection on the
back of the Call Server and Media Gateway.
Note: The MAU comes with the cable kits for the Call Server and Media
Gateway.
2 Insert the modular cable RJ-45 plug into the RJ-45 jack on the Ethernet
Adapter/MAU.
3 Insert the RJ-45 plug at the other end of the modular cable into the LAN hub.
4 Make the rest of the Ethernet connections as required using standard
This procedure is now complete
Ethernet connection rules.
Procedure 11
Install ICB cards
1 Identify the card slots selected for ICB card(s). Refer to Table 4 on page 46.
2 Make sure to properly place the PCMCIA hard drive card in the lower
faceplate PCMCIA slot.
3 Pull the top and bottom extractors away from the ICB faceplate.
4 Insert the ICB card into the card guides and carefully push it until it makes
contact with the backplane connector.
5 Push the top and the bottom extractors towards the faceplate to insert the ICB
card into the faceplate connector and to lock it in place.
6 Observe the red LED at the top of the faceplate (the card LED).
This LED blinks three times after the self-test successfully completes. When
the ICB software loads, the LED blinks three more times and then remains lit.
This takes approximately 45 seconds.
This procedure is now complete
7 Repeat Steps 1 through 6 for each additional ICB card.