JULY 2010 Auto BTU Start Up and Valve Timing
4.6 AUTO BTU START UP AND VALVE TIMING
The Auto BTU Start Up process, which takes
about an hour to complete, automatically
performs the following sequence of tasks:
1. Sets the timing for each valve.
2. Matches all the component peaks.
3. Adjusts the timed events based on peak
integration times.
4. Runs a calibration.
5. Checks the range and order of response
factors.
6. Adjusts the retention time deviations to
avoid peak overlapping.
You can also initiate a valve timing run, which
is the first step of the Auto BTU Start Up
process, independently of that process. See
“Starting a Valve Timing Run” on page 12 for
more information.
4.6.1 Initiating an Auto BTU Start Up Run
To launch the Auto BTU Start Up process, do
the following:
1. If the GC is currently performing an
analysis, select Halt from the Control menu
to put the GC in Idle mode after the current
analysis run.