![](http://pdfasset.owneriq.net/6/a0/6a07c5d1-8d45-45eb-bf37-5f260eec02a4/6a07c5d1-8d45-45eb-bf37-5f260eec02a4-bg49.png)
Site Preparation
Checklist
Item or Task
Performed
By Date Notes
Select the type of rack.
Plan rack location, including required space
clearances.
Secure rack to floor and building structure.
Acquire cables and connectors.
Locate sites for connection of system
grounding.
Calculate power budget and power margin.
Prepare for Router Installation 53