66 Installation and User’s Guide
2 Installing the System
To unpack the shipment crate containing the rack cabinet
The racked system is shipped upright secured to a pallet. Other system
components are shipped separately. Follow these instructions to unpack
and inspect the rack cabinet and the racked system components.
Required Tools
9/16 inch wrench or adjustable end wrench
Prying tool to remove packaging clamps
WARNING
Always wear safety glasses when removing the clamps and other
packing materials from the crate.
CAUTION
Be careful not to bend the clamps while removing them from the
shipping crate. You may reuse the clamps when the system is
repacked.
To unpack the shipment crate containing the rack cabinet
Step Action Notes
1 Remove the outer packing
crate.
a Remove the clamps holding the packing
crate top cover in place.
b Remove the top cover and set it aside.
c Remove the clamps holding the first
packing crate wall in place.
d Insure that two other people are available
to hold the last two walls in place as the
last set of clamps is removed.
e Remove the other walls.
f Set the loading ramp panel aside for now.
Which wall is removed first does not
matter.
In double-rack crates, the heaviest wall
is the loading ramp. In single-rack
crates, the loading ramp is shipped
inside the crate, placed on top of the
rack (it is a hinged assembly, shipped in
the folded position).
2 Remove the packaging
materials.
a Remove the foam top cover.
b Remove the plastic wrapping from the
system.