Samsung SMG-3200 Network Card User Manual


 
3-1
Chapter
3
Installing the System
This chapter provides SMG-3200 system installation procedures. First, step by step SMG-3200
system installation procedures are presented, and then environment configuration, board
installation, and power cable connecting procedures are explained.
Procedures on Installing the System
Following steps must be taken to install the SMG-3200 system.
1. Prepare the place to set up the system.
2. Move the packed system product to the installation place and unpack.
3. Installing in a rack. (Option)
4. Connect the grounding line.
5. Set up the jumper and install the daughter board of the board you want to load.
6. Install the board in a slot.
7. Connect cables.
8. Turn on the system after running a prior checkup.
Here are the detailed explanations of steps one to eight.