Cisco Systems Cisco CRS-1 Network Router User Manual


 
C-8
Cisco CRS-1 Carrier Routing System 16-Slot Multishelf System Site Planning Guide
OL-7422-04
Appendix C Site Planning Checklists
Multishelf System Preliminary Site Survey
Power
Is DC or AC power available for each
chassis? Is there a connection point on the
panel for each chassis?
Is a fuse access panel (FAP) available for
the equipment? Provide a connection
point on the FAP for each chassis.
Will an FAP be installed in time for the
routing system installation? Provide a
date when the FAP will be installed.
Is the FAP located in the same room as the
chassis?
Is there an AC power outlet (220 V or
110 V) located within 10 feet of each
chassis for PCs and test equipment?
Has proper grounding been provided for
the equipment? If not, when will the
grounding be available? Provide a
connection point for the grounding.
Are there any restrictions about when the
equipment can be powered on or electrical
work can be done? If so, describe them.
Are there special requirements for power
or power cables (for example, a different
gauge of wire)? If so, describe them.
Air Conditioning
Does the site have the air conditioning
capacity to handle the routing system? If
not, note what will be done to rectify the
lack of adequate cooling.
Describe the air conditioning at the site.
Control Plane, BITS, and Alarm Interfaces
Have you planned the layout and wiring
for the Cat6509 switches?
Have you planned terminal server and
console access for system components?
Will the chassis be connected to an
external alarm system? Has the cabling
been considered?
Supported Data Interfaces
Table C-4 Sample Routing System Preliminary Site Survey (continued)
Preliminary Site Survey