Appendix C Site Planning Checklists
Fabric Card Chassis Preliminary Site Survey
Air Conditioning
Does the site have the air conditioning capacity
to handle the chassis? If not, note what will be
done to provide adequate cooling.
Describe the air conditioning at the site.
Power
Is DC or AC power available for the chassis?
Is there a connection point on the panel for
the chassis?
Is a fuse access panel (FAP) available for the
equipment? Provide a connection point on
the FAP for each chassis.
Will an FAP be installed in time for the
routing system installation? Provide a date
when the FAP will be installed.
Is the FAP located in the same room as the
chassis?
Is there an AC power outlet (220 V or 110 V)
located within 10 feet of the chassis for PCs
and test equipment?
Has proper grounding been provided for the
equipment? If not, when will the grounding
be available? Provide a connection point for
the grounding.
Are there any restrictions about when the
equipment can be powered on or electrical
work can be done? If so, describe them.
Are there special requirements for power or
power cables (for example, a different gauge
of wire)? If so, describe them.
Chassis Cabling
Have you planned the cabling runs for the
optical array cables that are installed
between the fabric and line card chassis?
Have you planned the cabling runs for the
cables to connect the chassis to the Cat6509
switches?
Have you planned terminal server and
console access for the chassis?
Table C-2 Sample Routing System Preliminary Site Survey (continued)
Preliminary Site Survey