JVC 250 Projector User Manual


 
Chapter 8---Software and Protocol
8-8 Model 250 Service Manual
| Import Configuration |
| Start SEND TEXT Upload from |
| Host on Serial PORT A |
| -To Abort: |
| ->Stop Host Upload, |
| ->THEN Press
ESC to Abort |
=================================
6. Windows TERMINAL: Transfers + Send Text File....
6.1 Directories - set directory to desired upload directory (C:\TEMP)
6.2 File Name: - Type desired File Name (for example: import1.txt)
6.3 Select OK with mouse or press Enter key (upload begins)
6.4 Verify TERMINAL screen shows status line at bottom:
Stop, Pause, “% complete bar”, Sending: EXPORT1.TXT
6.5 Data transfer will continue until complete or an error occurs or the
User Aborts: Expect 10 minutes to import 20 sources (500,000 bytes)
at 9600 baud.
6.6 At successful end, TERMINAL will remove the bottom line.
7. Model 250 Menu:
When the projector detects the successful end of the transfer the following
screen is displayed:
=================================
| Import Configuration |
| IMPORT COMPLETE |
| New Configuration is active |
| |
| - Press ESC to Continue |
=================================
Press ESC to exit the projector Import operation and return to the
Maintenance Menu. There is a 10 second
pause before the screen is
redrawn.
8. USER ABORT:
Windows TERMINAL: FIRST press STOP to end the Host Upload
transfer.
Model 250 Menu: THEN press ESC to abort the projector Import
operation.
=================================
|
Import Failed
|
| IMPORT ABORTED BY USER |
| Old Data was Restored. |
| - STOP Host SEND DATA, |
| THEN Press ESC |
=================================