4.0 LOCATING THE STS2
This section provides instructions for leveling the STS2 and anchoring the unit to the floor, should
that be required.
For leveling feet details, see Figures 5 through 10.
4.1 Leveling and Anchoring the Unit to the Floor
The STS2 can be anchored to the concrete floor to ensure stability for the unit in the event of seismic
activity.
The seismic brackets are an option for the STS2 and are shipped separately from the unit when
ordered.
See Figures 11 through 13 for instructions and details for installing seismic anchoring.
4.2 Leveling of the Static Switch Without Anchoring
The Static Transfer Switch is furnished with casters and leveling feet. After final positioning of the
unit, adjust the leveling feet located in each corner of the frame base to level and stabilize the unit.
4.3 Leveling and Anchoring the Static Switch Using Floor Stand
The STS2 can be installed using the optional floor stand to support the unit instead of using the
raised floor. The STS2 can be rolled or placed using a lift on to the floor stand.
After final positioning of the unit, adjust the leveling feet located in each corner of the frame base to
level and stabilize the unit.
The floor stand can also be used to ensure the unit’s stability in the event of seismic activity by
anchoring the STS2 to the floor stand and to the concrete floor .
The seismic floor stand is shipped separately from the unit when ordered.
See Figures 33 through 44 for instructions and details for installing seismic floor stand.