Sun StorEdge Network 2 Gb FC Series Switches
Operating Mode Configuration
P
AGE 292 QLOGIC SWITCH INTEROPERABILITY GUIDE
VERSION 1.0, MARCH 2003
Operating Mode Configuration
Not applicable.
Sun StorEdge Specific Configuration
Not applicable.
QLogic Specific Configuration
Not applicable.
Successful Integration Checklist
Perform the following steps after the E-port connection has been established and the fabric has
had time to update. If everything verifies, the Sun and QLogic fabrics have successfully merged.
✓ Compare and verify that all Zoning information has been propagated on all switches.
✓ Verify that the correct Zone Set is activated.
✓ Compare and verify that all devices are in the Name Server of each switch.
✓ Verify that all initiators continue to detect and have access to all targets that existed prior to the
fabric merger.
After everything is verified, your fabric has merged successfully and no additional steps need to
be taken. If any of the above tasks did not complete successfully, please contact QLogic support.