American Power Conversion 400V Power Supply User Manual


 
Smart Distribution Panel with ATS 19
Operation
Automatic Operation
How to place the InfraStruXure Power Generation System in automatic operation
1. Ensure that mains is available. The generator will be signaled to start if mains is not available.
2. Ensure that the
/Manual/Auto switch on the generator control panel is in the Auto position.
3. Set the ATS Automatic Operation switch to Enable.
4. Check that the Not In Automatic Operation LED is not lit. See page 21 for information on
uncommon behavior of this LED.
“How the InfraStruXure Power Generation System Operates,” beginning on page 6,
provides a detailed summary of automatic operation of the InfraStruXure Power