Toshiba 4200FA Power Supply User Manual


 
24 4200FA Installation and Operation Manual
6.1.4 Power Connection Cable Routing and Conduit Placement 15/25/30 kVA
The following illustrates the proper cable routing that should be followed during the power
connection process of the 15/25/30 kVA.
Figure 6-3 15030kVA Cable Routing
CONDUIT
MOUNTING
PANEL
INPUT
CONDUIT
OUTPUT
CONDUIT
BATTERY
CONDUIT
Note:
1) Input and Output conductors
shall be installed in separate
conduits, and installed in
accordance with the latest
edition of NEC and the Local
Authority having jurisdiction.
2) Battery conductors shall be
installed in a separate conduit
and be of low resistance type.