Asante Technologies 9000 Switch User Manual


 
Installation Overview
Page 2-5
Installation Overview
The table below describes the steps needed to install the IntraChassis 9000. The
steps that are optional are labeled “optional” and the steps that are required are
labeled “required.” The sections that follow explain each step in detail.
Table 2-1 Installation Overview
Rack Mounting/Desktop Placement
The IntraChassis 9000 chassis can be installed in a standard 19-inch equipment
rack. It can also be placed on a stable horizontal surface with support
capabilities of 150 pounds (68.2 kilograms).
Important: The equipment rack or desk on which you
install your IntraChassis 9000 must be secure and stable.
Equipment racks must be fastened to the floor; desks must
be resting on a flat, stable surface.
Step Action to Be Taken
1(Required)
Open the box and check the contents.
See the Package Contents sheet for a complete list of the items
included with your IntraChassis 9000.
2(Required)
Install the IntraChassis 9000 chassis in an equipment rack or wall
rack, or prepare it for desktop placement. See page 2-5.
Important! When fully loaded, the IntraChassis 9000 can weigh
over 100 lbs (45 Kg). Use proper lifting equipment and tech-
niques to prevent back and other injuries.
3(Required)
Install the modules you have purchased for your IntraChassis 9000
and ensure each is properly seated and locked in place. See page 2-9.
4(Optional)
Install a second power supply module and make sure it is properly
seated in the chassis. See page 2-11.
5(Required)
Connect the power supply or power supplies.
See page 2-11.
6(Required)
Connect the modules to your network cables. See page 2-12.
7(Required)
Configure the IntraChassis 9000 for management capabilities.
See page 2-13.