IM584000300 Installation Instructions
Issue AB, April 3, 2013 Spec. No. 584000300 (Model 4015-X003)
Page 6 Chapter 1. General Information and Installation Acceptance Checklist
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy
Systems, North America, Inc. Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited.
INSTALLATION ACCEPTANCE CHECKLIST
General
The individual components of the DC Power System may be shipped as a complete
solution factory installed and wired in an IT rack, or may be shipped separately to be
installed in a customer provided IT rack.
Provided next is an Installation Acceptance Checklists for each option:
Factory Integrated System (List R1, R2)
Customer Integrated System (ship loose)
These Installation Acceptance Checklists help ensure proper installation and initial
operation of the system. As the procedures presented in Chapters 2 through 5 of this
document are completed, check the appropriate box on the appropriate Installation
Acceptance Checklist. If the procedure is not required to be performed for your
installation site, also check the box to indicate that the procedure was read. When
installation is done, ensure that each block in the appropriate Installation Acceptance
Checklist has been checked. Some of these procedures may have been factory
performed for you.
Note: The system is not powered up until the end of the Installation Acceptance
Checklist.
Note: Some of these procedures may have been performed at the factory for you.
Checklist –Factory Integrated System (List R1, R2)
Chapter 2. Installing the System
Equipment Inspection Completed
IT Rack Secured to Floor
Chapter 3. Making Electrical Connections
IT Rack Grounding Connection (Frame Ground) Made
AC Input Power and AC Input Equipment Grounding Connections Made
DC Load Distribution Connections to List 21-24 Distribution Sub-Rack(s) Made (if
furnished)
Battery Sub-Trays Installed in List 91-92 Battery Tray(s) (if furnished)
External Battery Connections Made (if required)
IB2 (ACU+ Controller Interface Board) Connections Made (if required)
ACU+ Controller Ethernet Connection Made (if required)
Power and Control Sub-Rack Bulk Output Connections Made (if required)
Chapter 4. Installing the Rectifiers
Rectifiers Installed
Chapter 5. Initially Starting the System
System Started, Configured, and Checked