Preinstallation steps (all bays)
Before you install drives in the server, verify that you have all the cables and any other
equipment specified in the documentation that comes with the drive. You might also
need to perform certain preinstallation activities. Some of the steps are required only
during the initial installation of an option.
1. Read “Safety information” on page 133, “Handling electrostatic discharge-
sensitive devices” on page 136, and the documentation that comes with the drive.
2. Choose the bay in which you want to install the drive.
3. Check the instructions that come with the drive to see if you need to set any
switches or jumpers on the drive.
Installing a drive in bay 1, 2, 3, or 4
To install a drive in bay 1, 2, 3, or 4, do the following:
1. Read the information in “Preinstallation steps (all bays)”.
2. Turn off the server and peripheral devices; then, remove the side cover (see
“Removing the side cover” on page 59 for details).
3. Insert a screwdriver into the slot on the right side of the filler panel, and remove
the filler panel from the server.