Polycom DOC2238A Network Router User Manual


 
Chapter 2 - Hardware Installation
2-4
Unpacking and Positioning the MGC+100
To unpack and position the MGC+100:
1. When you receive your MGC+100, inspect the equipment for damage
and verify that the components match the packing slip. If you did not
receive a component or if there is damage to the system, notify your
service representative immediately.
Figure 2-1: MGC+100 package
2. Place the MGC+100 unit on a stable flat surface in a location that meets
the MGC+ environment requirements, which are:
Operating temperature: 10°–40°C (50°–104°F) or 10°–35°C
(50°–95°F) when installed in a 19” rack
Humidity: 15%–90% non-condensing
Altitude: Up to 3,000m (10,000ft)
ESD: +8 kV
3. Release the clasp locks at the bottom, and lift the MGC+100 top cover.
Carrying Strap
Lock in Open Position
Wood Packing Case
Lock in Closed Position