Infortrend A16E-G2130-4 Power Supply User Manual


 
EonStor A16E-G2130-4 Installation and Hardware Reference Manual
power up the subsystem and configure the RAID array.
(See Section 4.4)
2.4.1 Installation Procedure Flowchart
Figure 2-1 shows a flowchart of the installation procedure. As you complete
each step, check off the “Done” box on the right. Please use this flowchart
in conjunction with the instructions that follow.
Figure 2-1: Installation Procedure Flowchart
2.5 Unpacking the Subsystem
Use the Unpacking Checklist in your package to verify package contents.
Carefully check the items contained in each box before proceeding with
installation.
NOTE:
A detailed packing list can be found in your product shipping package or
product CD.
The space within each package carton can be separated into upper and lower
levels.
Upper level: The two (2) foam packages on the upper level contain:
Sixteen (16) drive trays
Unpacking the Subsystem
2-6