Operator’s Guide
Emptying the Effluent Tanks
WARNING:
NOTE:
Wear protective gloves, a rubber apron, and goggles when you
empty the effluent tanks.
As soon as one of the effluent tanks is full, a message appears on the screen
advising that this tank must be emptied.
It is possible to touch Clear to suppress the message and to continue the
work for a while. When the message appears for the third time, it can no
longer be cleared.
Empty the full tank:
1. Open the front door at the bottom left of the paper processor. Position (1) marks
the drain valves to be opened to empty the effluent tanks.
2. Put a bucket under the respective drain valve. Open the valve and empty the
tank. Close the valve.
Perform the same procedure with the adjacent second valve.
CAUTION:
IMPORTANT:
Do not open both valves at the same time. The volume of both
tanks is 20 L.
• Do not open the drain valves in the vertical position on the right
side. They are used to empty the processing tanks CD, BX and
SB1 to SB4, for example, when a completely new tank preparation
has to be filled into single or all tanks.
• Check the pan (2): If it is full although the customer emptied the
tanks always in time, a technician must be called. The hose
systems could be defective.
8-38 KODAK PROFESSIONAL RP 30 Laser Printer