Kodak RP 30 Printer User Manual


 
Chemicals
Installing the Racks and Bringing the Tank Solutions to
Temperature
When you fill the tanks with the new mixes, they will appear only partially filled. When
you reinstall the racks in the tanks, the racks will displace more solution volume to fill
the tanks.
1. Install each rack by slowly lowering it into the tank; the rack will displace
additional volume to fill the tank and partially mix the solution.
2. When you have reinstalled all the racks, verify that all tanks are filled with
solution.
3. Restore power to the equipment.
4. Starting the recirculation pumps will complete the mixing of the solutions.
5. Let the processor come up to operating temperature.
Tank Temperature ºC
Developer 40.0 +/- 0.3
Bleach-Fix 38 +/- 2
Stabilizer 37 +/- 3
Preparing Replenisher
1. Fill 7 L (1.8 gal) of water in the Astor tank (1).
2. Fill the water tank until the upper one of the two float sensors is activated or the
overflow indicator sticks out of the tank.
3. Prior to the first paper transport, water must be used to wet the foam rollers of
the squeegee unit (2). Otherwise the wet paper could stick to the dry rollers.
1
2
KODAK PROFESSIONAL RP 30 Laser Printer 3-7