Chapter 10 Operator Panel Replacement 10-7
11. Place the removed OPNL on an antistatic mat.
12. Mount the replacement OPNL by following the removal instructions in Step 8
to Step 10 in reverse order.
Caution – Do not forcibly push the cable in when inserting it. If there is problem
with the connector pin, serious damage may result.
13. Insert the OPNL key, and then set the key to the Service position.
14. Switch on all main line switches for the AC section (ACS) in the power supply
system.
15. Confirm that the XSCF STANDBY LED (green) on the OPNL remains lit. If it is
blinking, wait until it remains lit.
16. Start (turn on power) all domains together. Take either of the following two
actions:
■ Press and hold down (for less than four seconds) the POWER switch on the
operator panel.
■ From a console that is connected to XSCF, execute the poweron -a command
of XSCF.
The power to all the domains is turned on, and then the power-on self test (POST)
is executed. When ok prompt displayed on the console of relevant domain, POST
is completed.
For details of the power-on operation, see Section 4.4.2, “Powering the Server On”
on page 4-19, and the SPARC Enterprise M3000/M4000/M5000/M8000/M9000
Servers XSCF User’s Guide.
17. Confirm that the replaced components are normal by using the showhardconf
or showstatus command of XSCF.
Unless "*" is displayed for the replacement OPNL, it is operating normally.
For details of the showhardconf command and showstatus command, see the
SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF User’s Guide,
the SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF Reference
Manual, or the man page.
Note – The showstatus command displays information on degraded components.