2.0 Scope
System Setup describes receiving and handling of the Galaxy PW™ 100 to 225kVA, a description of major compo-
nents, the battery cabinet, and definition of the control panel indicators, which includes electrical, mechanical and
environmental specifications.
MGE also recommends obtaining an MGE field service engineer for final installation and basic startup for single and
parallel units.
CAUTION Scheduling of the MGE Field Service Engineers typically should be done 7 to
10 days before they are required on-site. If the startup of the UPS is critical
to maintaining your schedule, please call the MGE toll free telephone number
at
1-800-438-7373 for assistance.
The MGE Field Service Engineers will
insure a
quick installation for the initial safe startup and configuration of your Galaxy PW™.
Final installation and start-up should be completed by a qualified MGE Field Service Engineer.
2.0.1 First steps by an on-site qualified Technical Engineer
Step 1. Unpack and position the unit.
Step 2. Connect the main (utility) power.
Step 3. Connect the power circuits.
2.0.2 Final steps by MGE Field Service Engineer
Step 4. Call MGE and wait for the MGE Field Service Engineer to complete the installation.
Step 5. The MGE Field Service Engineer finalizes installation and the startup process.
Optional: Procedure for temporary power prior to the final startup.
2.0.3 Required Equipment and Tools
The following equipment and tools are recommended for on-site installation:
Digital volt meter (DVM)
1/8 inch slotted screwdriver
Pallet jack/forklift
Conduit installation tools
Nut driver set