MGC-100 Hardware Installation
Unpacking and Positioning the MGC-100
To unpack and position the MGC-100:
1. When you receive your MGC-100, inspect the equipment for damage
and verify that the components match the packing slip. If you did not
receive a component or if there is damage to the system, notify your
service representative immediately.
Figure 2-1: MGC-100 package
2. Place the MGC-100 unit on a stable flat surface in a location that meets
the MGC environment requirements, which are:
Operating temperature: 10°–40°C (50°–104°F)
Humidity: 15%–90% non-condensing
Altitude: Up to 3,000m (10,000ft)
ESD: +8 kV
Carrying Strap
Lock in O
p
en Position
Wood Packing
C
ase
Lock in Closed Position