MGC Hardware and Installation Manual
2-17
To install the MPI-4/8 Network Interface Module:
1. Slide the MPI-4/8 Network Interface module into a free slot in the MGC
front panel.
2. Push the MPI-4/8 Network Interface module firmly into the Backplane,
making sure it is properly seated in its slot.
3. Tighten the screws on the front panel of the MGC-100 that secure the
MPI-4/8 Network Interface module.
To install the MPI Box on Top of the MCU:
1. Turn OFF power to the MCU and unplug it from AC power.
2. If the MCU is rack mounted, disconnect all the external cables, dismount
the MCU from the rack and place it on a desktop or work table.
If it is a standalone unit, remove the MCU side panels.
3. Remove the two Phillips screws on each side of the MCU (near the rear
panel).
front
rear
remove
screws