ADIC Scalar 1000 Network Card User Manual


 
Post-Repair Checklist 91
6-00020-02
SNC 5100
Post-Repair Checklist
It is important that the items in this checklist are verified after you have
completed a repair action. This ensures a successful reinstall of the product.
Table 4-1: Post-Repair Checklist
Step Actions Comments and References
1
Reinstall the SNC 5100
in its original location.
See Replacing the SNC 5100 on page 84
2
Ensure that the FC hosts
are turned off. if not,
disconnect the FC cables
now.
If you cannot turn off the FC hosts you must
disconnect the FC hosts before turning on the SNC
5100. This is a safety precaution that ensures that FC
hosts cannot perform any I/O to the SCSI target
devices prior to restoring the SNC 5100 configuration
in step 8, below.
3
Attach the Service
Terminal to the SNC
5100
None.
4
Turn on the SNC 5100. None.
5
Wait for the SNC 5100
to finish booting.
Within one minute, the Ready LED should start
flashing once per second and the Done executing
startup script message should be displayed on the
service terminal.
If not, go to Start MAP on page 42.
6
From the service
terminal, enter the
targets command.
See Service Port Command Reference on page 105.
If all attached SCSI devices are not shown, go to
Start MAP on page 42.
7
If you replaced the SNC
5100, configure the
network parameters.
Obtain the network parameters.