Emerson I-0021 Computer Accessories User Manual


 
4.5 Zero Calibration
90003482(2) [NGA-e (MLT-Software 3.2.X)] 07/98
NGA 2000
4 - 39
Display Status... Main... Channel Calib...
TAG
F1 F2 F3 F4 F5
Failures: No
Maintenance-Requests: No
Temperature: 20.0 C
Operation: Ready
0.0 100.0
Range: 1
37.50 ppm CH4
0.00 50.00
Measure Status... Channel Back...
TAG
F1 F2 F3 F4 F5
37.50 ppm
-- Analyzer Module Calibration --
Calibration procedure status...
Start span calibration procedure !
Expected span gas: 50.00 ppm
Span gas name: Methane
Start zero calibration procedure !
Expected zero gas: 0.00 ppm
Valves...
Valve position: Samplegas
Time & Date: 12:50:55 June 16, 1998
Measure Status... Channel Back...
TAG
F1 F2 F3 F4 F5
37.50 ppm
-- Analyzer Module Calibration --
Calibration procedure status...
Start span calibration procedure !
Expected span gas: 50.00 ppm
Span gas name: Methane
Start zero calibration procedure !
Expected zero gas: 0.00 ppm
Valves...
Valve position: Samplegas
Time & Date: 12:50:55 June 16, 1998
Change to the
menu "Analyzer
Module Calibration"
Press
F5
Caution:
Before starting zero
calibration, realize that
zero gas is available !
(See also section 5.1.1,
p. 5-5... !)
Note:
The zeroing of all measure-
ment ranges of the same
channel is running simulta-
neously.
Change to the
line "Start zero
calibration
procedure !"
Press once to
get the line "Start zero
calibration procedure !"
white on black.
Start the zero
calibration
Press
or