Emerson I-0021 Computer Accessories User Manual


 
4.6 Span Calibration
90003482(2) [NGA-e (MLT-Software 3.2.X)] 07/98
NGA 2000
4 - 45
Measure Cancel ! Back... More...
TAG
F1 F2 F3 F4 F5
50.00 ppm
-- Calibration Procedure Status --
Procedure status: Ready
Current/expected gas flow: Samplegas
Concentration in span gas units: 50.00 ppm
Last zero calibration: Success
Last span calibration: Success
Last span calibration was: Mon 06-08-1998 09:28:13
Successful zero+span calibrated ranges: 1+2+3+4
Remaining procedure time: 0 s
Last zero calibration was: Mon 06-08-1998 09:21:34
---------------------- Results ----------------------
Display Status... Main... Channel Calib...
TAG
F1 F2 F3 F4 F5
Failures: No
Maintenance-Requests: No
Temperature: 20.0 C
Operation: Ready
0.0 100.0
Range: 1 F.S.
50.00 ppm CH4
0.00 50.00
Change to the
single component
display of the
current channel
Press
F1
Options:
F4 key: Changing back
to the menu "Analyzer
Module Calibration".
F5 key: Changing to
the menu "Calibration
Deviations".
Single component
display appears after
spanning is done