Chapter 3
Installing the System
Setting Up the System
101
Figure 3-24 Installing the Front Blower Bezel
Step 3. Align the bezel over the nuts that are attached to the bracket at the front of the cabinet.
Step 4. Using a T-20 driver, tighten the two captive screws on the lower flange of the bezel.
NOTE Tighten the screws securely to prevent them from interfering with the door.
Step 5. Close the front door.
Wiring Check
WARNING LETHAL VOLTAGE HAZARD—Hazardous voltages may be present in the cabinet if
incorrectly wired into the site AC power supply. Always verify correct wiring and
product grounding before applying AC power to the cabinet. Failure to do so may
result in injury to personnel and damage to equipment.
Always verify that the AC power cable is correctly wired into the AC power supply before applying AC power
to the cabinet.
Verify the following items before applying AC power to the cabinet:
• Cabinet safety ground connects to the site electrical system ground and is not left floating or connected to
a phase.
NOTE The following identifies the minimum acceptable and the preferred methods of grounding. Use
the required method whenever possible.