Setting Up the System
After a site has been prepared, the system has been unpacked, and all components have been inspected, the
system can be prepared for booting.
Moving the System and Related Equipment to the Installation Site
Carefully move the cabinets and related equipment to the installation site but not into the final location. If
the system is to be placed at the end of a row, you must add side bezels before positioning the cabinet in its
final location. Check the path from where the system was unpacked to its final destination to make sure the
way is clear and free of obstructions.
WARNING If the cabinet must be moved up ramps, be sure to maneuver it using three people.
Unpacking and Installing the Blower Housings and Blowers
Each cabinet contains two blower housings and four blowers. Although similar in size, the blower housings for
each cabinet are not the same; one has a connector to which the other attaches. Use the following procedure to
unpack and install the housings and blowers:
Step 1. Unpack the housings from the cardboard box and set them aside.
The rear housing is labeled Blower 3 Blower 2. The front housing is labeled Blower 0 Blower 1.
CAUTION Do not lift the housing by the frame (Figure 3-12).
Figure 3-12 Blower Housing Frame
Step 2. Remove the cardboard from the blower housing (Figure 3-13).
Blower housing
frame
Handles