ADIC SNC 5100 Network Card User Manual


 
Fibre Channel MAP 63
6-00020-02
SNC 5100
Examine Cables
Caution
If in this procedure, you need to remove or replace the Fibre
Channel cable, you must stop I/O at the Fibre Channel host.
Step 1. Remove the cables.
Step 2. If any cables are obviously damaged, replace them.
Step 3. Use dusting spray/compressed gas to dust off optical connectors on
the GBIC and cable ends.
Step 4. Reconnect the cables.
Step 5. Perform Health Check.
For more information, see Perform Health Check on page 46.
Step 6. View the event log at viewing level 3.
For more information, see Table 9, Event Viewing Levels, on
page 42.
Step 7. If errors are gone, exit this MAP.
If errors persist, go to "Fibre Channel Loop Back Test".
Fibre Channel Loop Back Test
Caution
Before performing diagnostics, the Fibre Channel cables must be
removed from the SNC 5100. All I/O to the SNC 5100 must be
stopped.
Step 1. Attach a Fibre Channel loop back plug to the Fibre Channel port.
Step 2. If the front-panel FC Connection Status LED is not on, replace the
SNC 5100.
For more information, see Figure 4 on page 14.
Go to Before Removing or Replacing the Unit on page 82.
Continue through Replacing the SNC 5100 on page 84.