Fujitsu 2000 Server User Manual


 
CHAPTER 1 Installation Overview
1.1 Setup Workflow
1
Installation Overview CHAPTER 1
This chapter describes the workflow up to actual operation of the PRIMEQUEST2000 series server.
For an overview of the hardware and software and Product names and functions of the server, see the
PRIMEQUEST2000 Series General Description (C122-B025EN).
1.1 Setup Workflow
This section describes the workflow for the tasks required to prepare the PRIMEQUEST2000 series server for operation.
Setup work consists of tasks performed by a field engineer and other tasks performed by the user.
The setup workflow is described below.
Field engineers perform the following tasks on this product.
Customers are not allowed to perform these tasks under any circumstances. Otherwise, electric shock, injury, or fire may
result.
- Newly installing or moving equipment
- Removing the front, rear, and side covers
- Installing and removing built-in options
- Maintenance (repair and periodic diagnosis and maintenance)
1.1.1 Work performed by a field engineer
A field engineer sets up the unit. This includes the following tasks:
- Checking mounted components
- Preparing for main unit installation
- Checking partitions ... etc.
Remark
The following tasks need to be completed before the user starts the setup work:
- Unit setup by a field engineer
- MMB setup within the scope of responsibility of the field engineer
- Running test programs ... etc.