Fujitsu T5440 Server User Manual


 
132 SPARC Enterprise T5440 Server Service Manual June 2011
6. Slide the power distribution board up and out of the chassis.
Install the Power Distribution Board
1. Align the keyholes in the power distribution board with the corresponding
mushroom standoffs in the chassis.
2. Lower the power distribution board into the chassis.
3. Install the No. 2 Phillips screw.
4. Install the two 7 mm nuts securing the bus bars to the power distribution board.
5. Plug in the flex cable connector.
Ensure that the auxiliary power cable is routed under the flex cable connector.
6. Plug in the auxiliary power cable.
7. Install the flex cable retainer.
Place the retainer into position and tighten the captive No.2 Phillips screw.
Next Steps
“Install the Top Cover” on page 154
“Slide the Server Into the Rack” on page 155
“Install a Power Supply” on page 93
Note – Install all four power supplies.
“Connect the Power Cords to the Server” on page 157