Juniper Networks EX2200 Switch User Manual


 
CHAPTER 4
Site Preparation
Site Preparation Checklist for EX2200 Switches on page 33
General Site Guidelines for EX Series Switches on page 35
Site Electrical Wiring Guidelines for EX Series Switches on page 35
Environmental Requirements and Specifications for EX Series Switches on page 36
Site Preparation Checklist for EX2200 Switches
The checklist in Table 15 on page 33 summarizes the tasks you need to perform when
preparing a site for EX2200 switch installation.
Table 15: Site Preparation Checklist
DatePerformed ByFor More InformationItemor Task
Environment
“Environmental Requirements and
SpecificationsforEXSeriesSwitches”
on page 36
Verifythat environmental factorssuch as
temperatureandhumiditydonotexceedswitch
tolerances.
Power
Measure distance betweenexternal power
sources and switchinstallation site.
Locate sitesfor connection of system
grounding.
“PowerSpecifications forEX2200
Switches”on page47
Calculatethe powerconsumption and
requirements.
Hardware Configuration
“EX2200 SwitchesHardware
Overview”on page3
Choosethe number and types of switchesyou
wantto install.
Rackor Cabinet