Table 15: Site Preparation Checklist (continued)
DatePerformed ByFor More InformationItemor Task
“RackRequirements forEX2200
Switches”on page39
“CabinetRequirements forEX2200
Switches”on page40
Verifythat yourrackor cabinet meetsthe
minimum requirements forthe installation of
the switch.
“ClearanceRequirementsfor Airflow
and Hardware Maintenance for
EX2200 Switches”on page42
Planrackorcabinetlocation,includingrequired
spaceclearances.
Secure the rackor cabinetto the floorand
buildingstructure.
Wall
“Requirementsfor Mounting an
EX2200SwitchonaDesktoporWall”
on page 42
Verifythat the wallmeets the minimum
requirements forthe installation of the switch.
“ClearanceRequirementsfor Airflow
and Hardware Maintenance for
EX2200 Switches”on page42
Verifythatthereisappropriateclearanceinyour
selectedlocation.
Cables
Acquirecablesand connectors:
Determinethe number of cables needed
based on your planned configuration.
Reviewthe maximum distanceallowed for
eachcable.Choosethelengthofcablebased
on the distance betweenthe hardware
componentsbeing connected.
Planthe cableroutingand management.
Related
Documentation
General Safety Guidelines and Warnings for EX Series Switches on page 113
General Site Guidelines for EX Series Switches on page 35
Installing and Connecting an EX2200 Switch on page 51
Mounting an EX2200 Switch on page 53
Copyright ©2010,Juniper Networks,Inc.34
CompleteHardwareGuide forEX2200 EthernetSwitches